    1. All stations to measure beam-maps at L- and C-band (provided appropriate software is available at the telescopes) and send them to Keimpema. Update the table at https://deki.mpifr-bonn.mpg.de/Working_Groups/EVN_TOG/Beam_maps
    2. Upgrade to SDK9.4 first at the correlators then at the stations.
    3. Add Irbene to http://mark5-info.jive.nl
    4. All stations (except Wettzell): implement 80 Hz continuous calibration and update table at https://deki.mpifr-bonn.mpg.de/Working_Groups/EVN_TOG/Continuous_calibration_%2880_Hz%29
    5. JIVE: set up a wiki page, summarizing problems per station. Stations must give response before each TOG.
    6. Provide frequency information of the stations to de Vicente
    7. All stations: measure discrepancy between actual tracking of source and log information.
    8. All stations: provide ANTAB and RXG files to correlator.
    9. Send e-mail to stations with problems after results of Session II, 2016 have been published, as some/many of the problems were already reported and may have been fixed.
    10. If station’s amplitude calibration deviation > 0.1 must do on/off measurement. Reference here: http://www.radionet-eu.org/radionet3...:evnampcal.pdf
    11. Move calibration procedure to post-ob; discuss with Himwich to do this as post-ob is rarely included in the procedures.
    12. Cambell to provide list of stations that have not yet fully implemented data valid on/off.
    13. Update table https://deki.mpifr-bonn.mpg.de/Working_Groups/EVN_TOG/2Gbps on the wiki. In case of problems with the DBBC contact Gino Tuccari.
    14. If a station is not buying a FlexBuff, purchase disk packs
    15. Include Ir into the e-EVN in 2017