DBBC2/FiLA10G system setup

    Version as of 08:55, 27 Nov 2024

    to this version.

    Return to Version archive.

    View current version

    Pre-Checks

    • Check that the 1pps is connected to the DBBC2
    • Check that the 10MHz is connected to the DBBC2
    • Check that the IFs are connected (see Pico_DBBC.jpg )
    • Check that the serial cable is connected to the FiLA10G box
    • Check that the USB cable from the DBBC2 backside is NOT connected to the FiLA10G box
    • Check that all 3 VSI cables are connected to the FiLA10G box (2 coming from the DBBC2, one going to the Mark5B)
    • Check that one VSI cable of the FiLA10G box is connected to the Mark5 recorder

    Startup

    • power on the DBBC2 electronics (EL switch)
    • power on the DBBC2 PC (PC swich)
    • power on the FiLA10G box

    Loading the DBBC2 firmware

    • Log into the DBBC2 (user dbbc, password: ask Salvador/Helge); can be done also via remote desktop from mrt-vlbi
    • Depending on the observation mode (PFB, or DDC) there are two different firmwares to be loaded:
    • Polyphase Filterbank Mode (PFB)

    On the desktop double-click: "DBBC2 Control PFB v16..." icon (exact name can vary depending on the version)

    • Tunable Mode (DDC)

    On the desktop double-click: "DBBC2 Control DDC v105..." icon (exact name can vary depending on the version)

    • Reply 'y' to the question whether to configure, wait until the configuration is finished. During the process the LEDs on the DBBC2 frontside will change. Leave the window open after the configuration is finished.