Pre-Checks
- Check that 1pps cable is connected (backside)
- Check that 10MHz signal is connected (backside)
- Check that GPS signal is connected
- Check that GPS antenna is installed close to the window and that GPS satellites have been found (see below)
- Check that IFs are connected with LCP and RCP cables as labeled on the backside
- Check that optical fibre cables are connected to the Core3H boards inside the DBBC3 (for order see XXX).
- Check that optical fibre cables are connected to the Mark6 ethernet ports as labeled on the cables.
- Check that short cables connecting the pins "Out unfilt." "0-4 GHz In" on the backside are in place (see picture).
Startup
- Turn on main power switch (backside)
- Power on the electronics ("EL switch" on the backside)
- Wait at least one second before you proceed to the next step
- Power in the PC ("PC switch" on the backside)