    what date
    Modules from NOEMA now, and fringes Nn-Ef-Ys 28 Jun 2022
    Array tie EVN-KVN-VLBA 86 GHz done, now still missing ATCA+MP 20 Jun 2022
    All data transferred and modules available  
    Correlation of 7mm finished 13 Dec 2022
    Correlation of 3mm started 19 Dec 2022
    Correlation of 3mm finished 21 Dec 2022
    Packaging of v2 MJ002 finished with Mopra converted to linear 06 Feb 2023
    Released to PIs 07 Feb 2023
    Partial recorrelation (v2) of 3mm of scans with GLT (they had a YIG tuning error) 24 May 2023
     Releaser v2 to PIs  30 May 2023

    ...

    Version from 13:39, 24 May 2023

    This revision modified by jwagner (Ban)

    ...

    Current version

    This revision modified by jwagner (Ban)

    ...

    what date
    Modules from NOEMA now, and fringes Nn-Ef-Ys 28 Jun 2022
    Array tie EVN-KVN-VLBA 86 GHz done, now still missing ATCA+MP 20 Jun 2022
    All data transferred and modules available  
    Correlation of 7mm finished 13 Dec 2022
    Correlation of 3mm started 19 Dec 2022
    Correlation of 3mm finished 21 Dec 2022
    Packaging of v2 MJ002 finished with Mopra converted to linear 06 Feb 2023
    Released to PIs 07 Feb 2023
    Partial recorrelation (v2) of 3mm of scans with GLT (they had a YIG tuning error) 24 May 2023
    Releaser v2 to PIs 30 May 2023

    ...