01.07 - 08.07

    Table of contents
    No headers

    Version as of 09:09, 5 May 2024

    to this version.

    Return to Version archive.

    View current version

    enlightenedThe station is in local mode.

    enlightenedILT Operations may want to take over control at any moment. In such a case, I'll make the announcement to the

          observer.

    enlightenedPlease send your schedules to Masaya Kuniyoshi <mkuniyos@mpifr-bonn.mpg.de>.


    • 10:00 - 15:00 (01.July)    Andreas : hardware

    • 17:00 - 18:00 (01.July)    Masaya : software

    • 11:00 - 16:00 (04.July)    Masaya: software, pulsar (lofar3 and lofar4)

    • 16:00 - 17:00 (04.July)    James

    • 17:00 (04.July) - 09:00 (05.July)    Andreas : hardware

    • 09:00 (05.July) - 21:00 (06.July)    Evan : pulsar

     

    indecisionAris and Masaya use the lofar3.

    indecisionThe LOFAR fiber connection to Effelsberg will be down on Wednesday (6.July) between 7:30 and 9:00 in the morning, local time.
    indecisionThere will be a possible network downtime for the Effelsberg LOFAR link on Tuesday of next week (12.July) at some point between 05:00 and 07:00 (CEST). (Local mode observations should not be affected, but ILT observations would be.)