2022
code /date | code | Description |
21.2.2020 | 21020202_dbbc3_ddc | PV DBBC3 DDC_V Testing amplitude drop in the last 4 BBCs of Board C |
4.12.2020 | | NOEMA Phasing Test @ 3mm |
2020
code /date | code | Description |
21.2.2020 | 21020202_dbbc3_ddc | PV DBBC3 DDC_V Testing amplitude drop in the last 4 BBCs of Board C |
4.12.2020 | | NOEMA Phasing Test @ 3mm |
2019
code | Description |
4.4.2019 | 4Gbps test |
2018
code | Description |
t3mm19 | 3mm GLT commissioning: Ef,Eb,Ys,Gl |
| |
2017
Code | Description |
e17o31 | EHT Jan17 subset between Pico and APEX, DBBC3 and R2DBE |
e17d05_pv | EHT April 2017. Zerobaseline test between R2DBEs and DBBC3 at Pico |
2016
Code | Description |
b163a | GMVA fringe test. Primary goal was to confirm fringes to Pico |
t162a | DBBC2 fullband mode test |
a163a | DBBC2 fullband mode test |
e16c19 | APEX /SMTO fringe test with new APEX receiver |